A portion of the below grade sawmill support wall toward the stream side raceway had split apart, was undermined, and fallen away from its prior location. Engineering consultants will need to review the matter and provide advice on a plan to fix the situation.

Foundation Issues

            &

      Resolution

IMG_1802.jpg

An attempt to straighten the stream side wall resulted in a crack -- the wall needed to be replaced. Removing the road side wall required excavating the wall and creating a sloped surface for safety. The H & K Group provided the technology and material to create a new sawmill foundation.

_BDM5060.jpg
_BDM5063.jpg
_BDM5083.jpg
_BDM5088.jpg
_BDM5105.jpg
IMG_3136.jpg

Crushed stone was placed between the foundation footers for mill wall support and to prevent water pooling.

An H-beam found onsite was cut and modified to span the opening in the foundation and support the coming sawmill floor.

IMG_3138.jpg
IMG_3140.jpg

The tail race slopes were evened up and then seeded with grass and covered with straw.